Substation Scout

Bayles-Garards Fort 25kV

PJM queue ID Y2-088 Terminal status

Queue IDY2-088
Project nameBayles-Garards Fort 25kV
Status (as published)Withdrawn
SubstationGarards Fort
Point of interconnectionGarards Fort 25kV
CountyGreene
StatePA
Voltage25 kV
Capacity19.9 MW
Resource (as published)Natural Gas
Resource categoryGas (normalised for filtering)
Target commercial operation2015-06-30
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy19.9
Mw Capacity19.9
Mfo19.9
Withdrawn Date1/20/2017

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.