Kings Creek 25kV

PJM queue ID Y1-085 Terminal status

Queue IDY1-085
Project nameKings Creek 25kV
Status (as published)Withdrawn
SubstationKings Creek
Point of interconnectionKings Creek 25kV
CountySomerset
StateMD
Voltage25 kV
Capacity0 MW (0 MW as filed — net change or energy-only)
Resource (as published)Biomass
Resource categoryOther (normalised for filtering)
Target commercial operation2013-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy4.4
Mw Capacity0
Mfo4.4
Withdrawn Date10/4/2012