Felicity 69kV

PJM queue ID Y1-023 Terminal status

Queue IDY1-023
Project nameFelicity 69kV
Status (as published)Withdrawn
SubstationFelicity
Point of interconnectionFelicity 69kV
CountyUnknown
StateOH
Voltage69 kV
Capacity7.6 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2013-10-22
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy20
Mw Capacity7.6
Mfo20
Withdrawn Date10/17/2012

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.