Substation Scout

Cooper

PJM queue ID Y1-022 Terminal status

Queue IDY1-022
Project nameCooper
Status (as published)Withdrawn
SubstationCooper
Point of interconnectionCooper
CountyYork
StatePA
VoltageNot reported
Capacity3.8 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2013-10-21
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy10
Mw Capacity3.8
Mfo10
Withdrawn Date6/21/2013

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.