Shenango-Hoytdale 345kV

PJM queue ID Y1-015 Terminal status

Queue IDY1-015
Project nameShenango-Hoytdale 345kV
Status (as published)Withdrawn
SubstationShenango-Hoytdale
Point of interconnectionShenango-Hoytdale 345kV
CountyLawrence
StatePA
Voltage345 kV
Capacity870 MW
Resource (as published)Natural Gas
Resource categoryGas (normalised for filtering)
Target commercial operation2015-06-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy1000
Mw Capacity870
Mfo1000
Withdrawn Date7/29/2014

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.