Substation Scout

Worton 12kV

PJM queue ID Y1-014 Terminal status

Queue IDY1-014
Project nameWorton 12kV
Status (as published)Withdrawn
SubstationWorton
Point of interconnectionWorton 12kV
CountyKent
StateMD
Voltage12 kV
Capacity0 MW (0 MW as filed — net change or energy-only)
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2012-06-15
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy1.6
Mw Capacity0
Mfo1.6
Withdrawn Date8/17/2012

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.