Tasley-Kellam 69kV

PJM queue ID Y1-008 Terminal status

Queue IDY1-008
Project nameTasley-Kellam 69kV
Status (as published)Withdrawn
SubstationTasley-Kellam
Point of interconnectionTasley-Kellam 69kV
CountyAccomack
StateVA
Voltage69 kV
Capacity6.5 MW
Resource (as published)Wind
Resource categoryWind (normalised for filtering)
Target commercial operation2014-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy50
Mw Capacity6.5
Mfo50
Withdrawn Date3/26/2013