PJM queue ID Y1-006 Terminal status
| Queue ID | Y1-006 |
|---|---|
| Project name | Poplar Camp |
| Status (as published) | Withdrawn |
| Substation | Jubal Early-Austinville |
| Point of interconnection | Jubal Early-Austinville 138kV |
| County | Carroll |
| State | VA |
| Voltage | 138 kV |
| Capacity | 9.4 MW |
| Resource (as published) | Wind |
| Resource category | Wind (normalised for filtering) |
| Target commercial operation | 2023-03-01 |
| Source dataset | serial |
Additional filed fields
| Project Type | Generation Interconnection |
|---|---|
| Mw Energy | 72 |
| Mw Capacity | 9.36 |
| Mfo | 72 |
| Withdrawn Date | 10/17/2021 |