Substation Scout

Allerton Road Solar Farm

PJM queue ID X4-043 Terminal status

Queue IDX4-043
Project nameAllerton Road Solar Farm
Status (as published)Withdrawn
SubstationClinton
Point of interconnectionClinton
CountyHunterdon
StateNJ
VoltageNot reported
Capacity3 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2015-06-30
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy8
Mw Capacity3.04
Mfo8
Withdrawn Date9/19/2012

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.