Upper Deerfield 12kV

PJM queue ID X4-029 Terminal status

Queue IDX4-029
Project nameUpper Deerfield 12kV
Status (as published)Withdrawn
SubstationUpper Deerfield
Point of interconnectionUpper Deerfield 12kV
CountyCumberland
StateNJ
Voltage12 kV
Capacity0 MW (0 MW as filed — net change or energy-only)
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2013-01-02
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy10
Mw Capacity0
Mfo10
Withdrawn Date6/8/2012