Dickerson 230kV

PJM queue ID X3-088 Terminal status

Queue IDX3-088
Project nameDickerson 230kV
Status (as published)Withdrawn
SubstationDickerson
Point of interconnectionDickerson 230kV
CountyMontgomery
StateMD
Voltage230 kV
Capacity440 MW
Resource (as published)Natural Gas
Resource categoryGas (normalised for filtering)
Target commercial operation2016-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy440
Mw Capacity440
Mfo440
Withdrawn Date6/21/2012