Substation Scout

Massey 69kV

PJM queue ID X3-073 Terminal status

Queue IDX3-073
Project nameMassey 69kV
Status (as published)Withdrawn
SubstationMassey
Point of interconnectionMassey 69kV
CountyKent
StateMD
Voltage69 kV
Capacity3.7 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2013-03-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy9.8
Mw Capacity3.72
Mfo9.8
Withdrawn Date3/12/2012

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.