Fairfield Twp 1 12kV

PJM queue ID X3-060 Terminal status

Queue IDX3-060
Project nameFairfield Twp 1 12kV
Status (as published)Withdrawn
SubstationFairfield Twp 1
Point of interconnectionFairfield Twp 1 12kV
CountyCumberland
StateNJ
Voltage12 kV
Capacity0 MW (0 MW as filed — net change or energy-only)
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2012-09-30
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy2
Mw Capacity0
Mfo2
Withdrawn Date11/2/2011

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.