Substation Scout

Hough Solar Farm

PJM queue ID X3-054 Terminal status

Queue IDX3-054
Project nameHough Solar Farm
Status (as published)Withdrawn
SubstationSussex
Point of interconnectionSussex
CountySussex
StateNJ
VoltageNot reported
Capacity1.9 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2015-06-30
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy4.9
Mw Capacity1.9
Mfo4.9
Withdrawn Date11/13/2013

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.