Substation Scout

Warfield I

PJM queue ID X3-043 Terminal status

Queue IDX3-043
Project nameWarfield I
Status (as published)Withdrawn
SubstationLumberton
Point of interconnectionLumberton 69kV
CountyBurlington
StateNJ
Voltage69 kV
Capacity4.6 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2015-10-15
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy12
Mw Capacity4.56
Mfo12
Withdrawn Date1/5/2015