Substation Scout

Shelby-S.W. Lima 345kV

PJM queue ID X3-030 Terminal status

Queue IDX3-030
Project nameShelby-S.W. Lima 345kV
Status (as published)Withdrawn
SubstationShelby-S.W. Lima
Point of interconnectionShelby-S.W. Lima 345kV
CountyMarion
StateOH
Voltage345 kV
Capacity31.9 MW
Resource (as published)Wind
Resource categoryWind (normalised for filtering)
Target commercial operation2015-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy245
Mw Capacity31.85
Mfo245
Withdrawn Date5/30/2013

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.