6011 Greenwich Windpark, LLC

PJM queue ID X3-023 Terminal status

Queue IDX3-023
Project name6011 Greenwich Windpark, LLC
Status (as published)Withdrawn
SubstationS. Greenwich-Willard
Point of interconnectionS. Greenwich-Willard 69kV
CountyHuron
StateOH
Voltage69 kV
Capacity7.8 MW
Resource (as published)Wind
Resource categoryWind (normalised for filtering)
Target commercial operation2017-12-31
Source datasetserial

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy60
Mw Capacity7.8
Mfo60
Withdrawn Date8/5/2016