New Market 69kV

PJM queue ID X3-009 Terminal status

Queue IDX3-009
Project nameNew Market 69kV
Status (as published)Withdrawn
SubstationNew Market
Point of interconnectionNew Market 69kV
CountyDorchester
StateMD
Voltage69 kV
Capacity7.6 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2017-06-01
Source datasetserial

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy20
Mw Capacity7.6
Mfo20
Withdrawn Date8/24/2012