Substation Scout

Greenville Solar

PJM queue ID X3-002 Terminal status

Queue IDX3-002
Project nameGreenville Solar
Status (as published)Withdrawn
SubstationGreenville
Point of interconnectionGreenville 12kV
CountyDarke
StateOH
Voltage12 kV
Capacity1.3 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2017-12-31
Source datasetserial

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy3.38
Mw Capacity1.28
Mfo3.38
Withdrawn Date9/17/2018

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.