Queue IDX2-099
Project nameSparta Solar Farm
Status (as published)Withdrawn
SubstationSparta-Woodruff's Gap
Point of interconnectionSparta-Woodruff's Gap 34kV
CountySussex
StateNJ
Voltage34 kV
Capacity3.8 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2014-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy10
Mw Capacity3.8
Mfo10
Withdrawn Date3/14/2013