Substation Scout

Sandyston Solar Farm

PJM queue ID X1-114 Terminal status

Queue IDX1-114
Project nameSandyston Solar Farm
Status (as published)Withdrawn
SubstationHoliday Lakes
Point of interconnectionHoliday Lakes 12kV
CountySussex
StateNJ
Voltage12 kV
Capacity0.8 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2014-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy2
Mw Capacity0.76
Mfo2
Withdrawn Date5/3/2016

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.