Hopatcong

PJM queue ID X1-107 Terminal status

Queue IDX1-107
Project nameHopatcong
Status (as published)Withdrawn
SubstationHopatcong
Point of interconnectionHopatcong
CountySussex
StateNJ
VoltageNot reported
Capacity1.1 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2012-02-28
Source datasetserial

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy2.8
Mw Capacity1.06
Mfo2.8
Withdrawn Date9/6/2011

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.