Substation Scout

Newport 12kV

PJM queue ID X1-092 Terminal status

Queue IDX1-092
Project nameNewport 12kV
Status (as published)Withdrawn
SubstationNewport
Point of interconnectionNewport 12kV
CountyCumberland
StateNJ
Voltage12 kV
Capacity0 MW (0 MW as filed — net change or energy-only)
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2012-08-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy1.91
Mw Capacity0
Mfo1.91
Withdrawn Date10/6/2011

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.