Flemington Solar Farm

PJM queue ID X1-088 Terminal status

Queue IDX1-088
Project nameFlemington Solar Farm
Status (as published)Withdrawn
SubstationFranklin #2
Point of interconnectionFranklin #2
CountyHunterdon
StateNJ
VoltageNot reported
Capacity9 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2012-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy17
Mw Capacity9
Mfo17
Withdrawn Date8/13/2013