Emerson Creek Wind Farm

PJM queue ID X1-027A_AT12 Terminal status

Queue IDX1-027A_AT12
Project nameEmerson Creek Wind Farm
Status (as published)Withdrawn
SubstationDavis Besse-Beaver
Point of interconnectionDavis Besse-Beaver 345kV
CountyHuron
StateOH
Voltage345 kV
Capacity65 MW
Resource (as published)Wind
Resource categoryWind (normalised for filtering)
Target commercial operation2018-04-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy500
Mw Capacity65
Mfo500
Withdrawn Date7/18/2018

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.