Substation Scout

Mechanicsville

PJM queue ID X1-023 Terminal status

Queue IDX1-023
Project nameMechanicsville
Status (as published)Withdrawn
SubstationMechanicsville
Point of interconnectionMechanicsville
CountySt. Mary's
StateMD
VoltageNot reported
Capacity2.3 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2012-04-30
Source datasetserial

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy6
Mw Capacity2.28
Mfo6
Withdrawn Date4/8/2011

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.