Substation Scout

Vineland #2 12kV

PJM queue ID W4-090 Terminal status

Queue IDW4-090
Project nameVineland #2 12kV
Status (as published)Withdrawn
SubstationVineland #2
Point of interconnectionVineland #2 12kV
CountyCumberland
StateNJ
Voltage12 kV
Capacity0 MW (0 MW as filed — net change or energy-only)
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2011-06-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy1.34
Mw Capacity0
Mfo1.34
Withdrawn Date6/19/2014

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.