Substation Scout

Big Hill Solar Farm

PJM queue ID W4-072 Terminal status

Queue IDW4-072
Project nameBig Hill Solar Farm
Status (as published)Withdrawn
SubstationEnglishtown-Rt. 33 Sw Point
Point of interconnectionEnglishtown-Rt. 33 Sw Point 34.5kV
CountyMonmouth
StateNJ
Voltage34.5 kV
Capacity6.1 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2014-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy16
Mw Capacity6.08
Mfo16
Withdrawn Date10/23/2015

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.