Substation Scout

New Creek Mountain Energy Storage

PJM queue ID W4-037 Terminal status

Queue IDW4-037
Project nameNew Creek Mountain Energy Storage
Status (as published)Withdrawn
SubstationBismark
Point of interconnectionBismark 500kV
CountyGrant
StateWV
Voltage500 kV
Capacity0 MW (0 MW as filed — net change or energy-only)
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2018-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy32
Mw Capacity0
Mfo160
Withdrawn Date11/5/2018

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.