Substation Scout

West Portal 4.8kV

PJM queue ID W4-032 Terminal status

Queue IDW4-032
Project nameWest Portal 4.8kV
Status (as published)Withdrawn
SubstationWest Portal 4.8kV
Point of interconnectionWest Portal 4.8kV
CountyHunterdon
StateNJ
VoltageNot reported
Capacity0 MW (0 MW as filed — net change or energy-only)
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2011-12-22
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy1.5
Mw Capacity0
Mfo1.5
Withdrawn Date4/4/2012

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.