Carbon Limestone Landfil Gas to Electricity Facility
PJM queue ID W4-001A_AT9 Terminal status
| Queue ID | W4-001A_AT9 |
|---|---|
| Project name | Carbon Limestone Landfil Gas to Electricity Facility |
| Status (as published) | Deactivated |
| Substation | Lowellville |
| Point of interconnection | Lowellville 69kV |
| County | Mahoning |
| State | OH |
| Voltage | 69 kV |
| Capacity | 3.2 MW |
| Resource (as published) | Methane |
| Resource category | Gas (normalised for filtering) |
| Target commercial operation | 2012-12-31 |
| Source dataset | serial |
Additional filed fields
| Project Type | Generation Interconnection |
|---|---|
| Mw Energy | 3.2 |
| Mw Capacity | 3.2 |
| Mfo | 24 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.