Substation Scout

Kanawha River 138kV

PJM queue ID W3-161 Terminal status

Queue IDW3-161
Project nameKanawha River 138kV
Status (as published)Withdrawn
SubstationKanawha River
Point of interconnectionKanawha River 138kV
CountyFayette
StateWV
Voltage138 kV
Capacity13 MW
Resource (as published)Other
Resource categoryOther (normalised for filtering)
Target commercial operation2013-06-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy13
Mw Capacity13
Mfo13
Withdrawn Date2/16/2012

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.