Substation Scout

Stow Creek Township 12kV

PJM queue ID W3-157 Terminal status

Queue IDW3-157
Project nameStow Creek Township 12kV
Status (as published)Withdrawn
SubstationStow Creek Township
Point of interconnectionStow Creek Township 12kV
CountyCumberland
StateNJ
Voltage12 kV
Capacity0.7 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2011-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy1.7
Mw Capacity0.65
Mfo1.7
Withdrawn Date7/18/2013

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.