Pequest-Washington 34.5kV

PJM queue ID W3-144 Terminal status

Queue IDW3-144
Project namePequest-Washington 34.5kV
Status (as published)Withdrawn
SubstationPequest-Washington
Point of interconnectionPequest-Washington 34.5kV
CountyWarren
StateNJ
Voltage34.5 kV
Capacity3 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2012-03-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy8
Mw Capacity3
Mfo8
Withdrawn Date4/11/2012