Substation Scout

Kendallville 138kV

PJM queue ID W3-060 Terminal status

Queue IDW3-060
Project nameKendallville 138kV
Status (as published)Withdrawn
SubstationKendallville
Point of interconnectionKendallville 138kV
CountyNoble
StateIN
Voltage138 kV
Capacity15.6 MW
Resource (as published)Wind
Resource categoryWind (normalised for filtering)
Target commercial operation2012-11-01
Source datasetserial

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy120
Mw Capacity15.6
Mfo120
Withdrawn Date11/14/2011