Substation Scout

Allen Junction-Lyons 138kV

PJM queue ID W3-059B_AT7 Terminal status

Queue IDW3-059B_AT7
Project nameAllen Junction-Lyons 138kV
Status (as published)Withdrawn
SubstationAllen Junction-Lyons
Point of interconnectionAllen Junction-Lyons 138kV
CountyFulton
StateOH
Voltage138 kV
Capacity12.7 MW
Resource (as published)Wind
Resource categoryWind (normalised for filtering)
Target commercial operation2010-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy97.6
Mw Capacity12.69
Mfo97.6
Withdrawn Date2/2/2012

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.