Warfield II

PJM queue ID W3-057 Terminal status

Queue IDW3-057
Project nameWarfield II
Status (as published)Withdrawn
SubstationLumberton
Point of interconnectionLumberton 69kV
CountyBurlington
StateNJ
Voltage69 kV
Capacity7.6 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2015-10-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy20
Mw Capacity7.6
Mfo20
Withdrawn Date1/5/2016

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.