Substation Scout

Mackeys-Riders Creek 115kV

PJM queue ID W3-054 Terminal status

Queue IDW3-054
Project nameMackeys-Riders Creek 115kV
Status (as published)Withdrawn
SubstationMackeys-Riders Creek
Point of interconnectionMackeys-Riders Creek 115kV
CountyTyrell
StateNC
Voltage115 kV
Capacity19.5 MW
Resource (as published)Wind
Resource categoryWind (normalised for filtering)
Target commercial operation2013-09-30
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy150
Mw Capacity19.5
Mfo150
Withdrawn Date5/28/2012

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.