Jacksons Ferry-Peak Creek 138kV

PJM queue ID W3-021 Terminal status

Queue IDW3-021
Project nameJacksons Ferry-Peak Creek 138kV
Status (as published)Withdrawn
SubstationJacksons Ferry-Peak Creek
Point of interconnectionJacksons Ferry-Peak Creek 138kV
CountyPulaski
StateVA
Voltage138 kV
Capacity9.1 MW
Resource (as published)Wind
Resource categoryWind (normalised for filtering)
Target commercial operation2013-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy70
Mw Capacity9.1
Mfo70
Withdrawn Date3/2/2012