Fostoria Central-Galion (FE) 345kV

PJM queue ID W3-005 Terminal status

Queue IDW3-005
Project nameFostoria Central-Galion (FE) 345kV
Status (as published)Withdrawn
SubstationFostoria Central-Galion (FE)
Point of interconnectionFostoria Central-Galion (FE) 345kV
CountyHuron
StateOH
Voltage345 kV
Capacity65 MW
Resource (as published)Wind
Resource categoryWind (normalised for filtering)
Target commercial operation2013-11-30
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy500
Mw Capacity65
Mfo500
Withdrawn Date6/18/2014

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.