Lincoln Solar Farm

PJM queue ID W2-094 Terminal status

Queue IDW2-094
Project nameLincoln Solar Farm
Status (as published)Withdrawn
SubstationLincoln
Point of interconnectionLincoln 13.2kV
CountyAdams
StatePA
Voltage13.2 kV
Capacity1.1 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2016-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy3
Mw Capacity1.1
Mfo3