Bluff Point 138kV

PJM queue ID W2-068 Terminal status

Queue IDW2-068
Project nameBluff Point 138kV
Status (as published)Withdrawn
SubstationBluff Point
Point of interconnectionBluff Point 138kV
CountyMercer
StateOH
Voltage138 kV
Capacity19.5 MW
Resource (as published)Wind
Resource categoryWind (normalised for filtering)
Target commercial operation2011-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy150
Mw Capacity19.5
Mfo150
Withdrawn Date1/31/2012