Substation Scout

Engle 69kV

PJM queue ID W2-062 Terminal status

Queue IDW2-062
Project nameEngle 69kV
Status (as published)Withdrawn
SubstationEngle
Point of interconnectionEngle 69kV
CountyPerry
StateKY
Voltage69 kV
Capacity12.1 MW
Resource (as published)Biomass
Resource categoryOther (normalised for filtering)
Target commercial operation2012-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy12.1
Mw Capacity12.1
Mfo62.1
Withdrawn Date8/30/2010

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.