Powerton-Goodings Grove 345kV

PJM queue ID W2-046 Terminal status

Queue IDW2-046
Project namePowerton-Goodings Grove 345kV
Status (as published)Withdrawn
SubstationPowerton-Goodings Grove
Point of interconnectionPowerton-Goodings Grove 345kV
CountyLivingston
StateIL
Voltage345 kV
Capacity58.5 MW
Resource (as published)Wind
Resource categoryWind (normalised for filtering)
Target commercial operation2013-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy450
Mw Capacity58.5
Mfo450
Withdrawn Date12/7/2011

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.