Preble Solar Energy

PJM queue ID W2-040 Terminal status

Queue IDW2-040
Project namePreble Solar Energy
Status (as published)Withdrawn
SubstationCamden
Point of interconnectionCamden 69kV
CountyPreble
StateOH
Voltage69 kV
Capacity7.6 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2018-06-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy20
Mw Capacity7.6
Mfo20
Withdrawn Date1/23/2020