Suncatcher Clean Energy

PJM queue ID W2-026 Terminal status

Queue IDW2-026
Project nameSuncatcher Clean Energy
Status (as published)Withdrawn
SubstationGlassboro Road
Point of interconnectionGlassboro Road
CountyGloucester
StateNJ
VoltageNot reported
Capacity0 MW (0 MW as filed — net change or energy-only)
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2013-04-30
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy1.5
Mw Capacity0
Mfo1.5
Withdrawn Date5/14/2013