Substation Scout

Kearny 138kV

PJM queue ID W2-024 Terminal status

Queue IDW2-024
Project nameKearny 138kV
Status (as published)Withdrawn
SubstationKearny
Point of interconnectionKearny 138kV
CountyMiddlesex
StateNJ
Voltage138 kV
Capacity625 MW
Resource (as published)Natural Gas
Resource categoryGas (normalised for filtering)
Target commercial operation2014-05-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy625
Mw Capacity625
Mfo625
Withdrawn Date11/29/2011

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.