Substation Scout

Pantego Wind Farm

PJM queue ID W2-022 Terminal status

Queue IDW2-022
Project namePantego Wind Farm
Status (as published)Withdrawn
SubstationPantego
Point of interconnectionPantego 115kV
CountyHyde
StateNC
Voltage115 kV
Capacity9.6 MW
Resource (as published)Wind
Resource categoryWind (normalised for filtering)
Target commercial operation2018-10-15
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy73.6
Mw Capacity9.57
Mfo73.6
Withdrawn Date11/22/2016

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.