Substation Scout

Pruntytown 138kV

PJM queue ID W2-005 Terminal status

Queue IDW2-005
Project namePruntytown 138kV
Status (as published)Withdrawn
SubstationPruntytown
Point of interconnectionPruntytown 138kV
CountyTaylor
StateWV
Voltage138 kV
Capacity30 MW
Resource (as published)Hydro
Resource categoryHydro (normalised for filtering)
Target commercial operation2013-10-30
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy30
Mw Capacity30
Mfo30
Withdrawn Date12/16/2010

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.