Substation Scout

Buena 12kV

PJM queue ID W1-095 Terminal status

Queue IDW1-095
Project nameBuena 12kV
Status (as published)Withdrawn
SubstationBuena
Point of interconnectionBuena 12kV
CountyAtlantic
StateNJ
Voltage12 kV
Capacity7 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2011-07-21
Source datasetserial

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy18
Mw Capacity7.02
Mfo18
Withdrawn Date1/13/2011